The Snowy 2.0 team recently reached a massive milestone in the project with the successful first tunnel lining concrete pour completed at the Tantagara site on the Snowy 2.0 Project.

Together with Whittens, we've finished the first 10 metres of the 50 metre transition tunnel. This tunnel forms a critical link between the water intake diffuser, gate shaft and the 17 kilometre headrace tunnel.

Milestone in Number

  • 566.5 square metres of formwork

  • 108 tonnes of steel reinforcement

  • 800 cubic metres of concrete

  • Base, walls and crown poured in stages

  • Total pour time: 44 hrs 45 mins

Ends -

About the Project

Clough and its parent company, Webuild, are part of Future Generation Joint Venture - FGJV, the principal contractor for project owner Snowy Hydro, delivering the iconic Snowy 2.0, a major Snowy Scheme expansion underpinning Australia’s transition to a renewable energy future.